MATERIAL MASTER

MM01建立缺省值,如圖:

2、字段狀態的組合控制

a、字段狀態的優先級,由高往低

HIDE

diaplay

reqd entry

opt. entry

b、字段狀態五個組合

行業領域 M

工廠關聯字段 0001

事務代碼(mm02/mm01/mm03)

採購類型 (E OR F)

物料類型 (roh,halb,fert)

c,字段組合的優先級和組合知道,首先就需要知道字段的ID,如:MARC-EKGRP

在SPRO->Logistics - General->Material Master->Field Selection->Assign Fields to Field Selection Groups(OMSR)中得知它的組號是239

行業領域關聯字段:

SPRO->Logistics - General->Material Master->Field Selection->Define Industry Sectors and Industry-Sector-Specific Field Selection

工廠關聯字段

SPRO->Logistics - General->Material Master->Field Selection->Define Plant-Specific Field Selection and Plant-Specific Screen Selection

物料類型關聯字段

SPRO->Logistics - General->Material Master->Basic Settings->Material Types->Define Attributes of Material Types

維護字段

在上面的五個組合中分別維護

SPRO->Logistics - General->Material Master->Field Selection->Maintain Field Selection for Data Screens(OMS9)

3、物料類型

SPRO->Logistics - General->Material Master->Basic Settings->Material Types->Define Attributes of Material Types

4、定義物料組

SPRO->Logistics - General->Material Master->Settings for Key Fields->Define Material Groups(OMSF)

5、定義計量單位組

SPRO->Logistics - General->Material Master->Settings for Key Fields->Define Units of Measure Groups

6、定義物料號碼

SPRO->Logistics - General->Material Master->Basic Settings->Material Types->Define Number Ranges for Each Material Type(MMNR)

7、定義物料狀態

SPRO->Logistics - General->Material Master->Settings for Key Fields->Define Material Statuses(OMS4)

时间: 2024-08-15 20:53:00

MATERIAL MASTER的相关文章

Price Control V or S in Material Type (Price control in material master )

When is it useful to use the price control V or S in Material Master?  Do I have to follow the SAP standard setting in the material type for the following material types: - ROH (Raw materials) -> moving average price - HALB (Semifinished products) ->

Material master screens and fields

Weblinks ::: Enhancing Material Master :    http://scn.sap.com/docs/DOC-47544 Material master screens and fields : http://scn.sap.com/docs/DOC-52909 http://help.sap.com/saphelp_45b/helpdata/en/64/1a39516e36d1118b3f0060b03ca329/content.htm

Cross-plant material status in Material Master (Basic data 1)

1. Is Blocking Key assigned to material master in basic data 1 view in  X plant material status, if yes, remove blocking key and create PR & PO. Or check  source list(ME01) is  material blocked for procurement, if yes, remove it and save .Now  go for

Special Procurement Type for Costing (Costing View in Material Master )

http://help.sap.com/saphelp_470/helpdata/en/7e/cb7f5643a311d189ee0000e81ddfac/content.htm Special Procurement in Costing  Use A BOM can include materials produced not in the plant of the finished product, but in another plant, or externally. You can

SAP Actual Costing with Material Ledger 激活实际成本后台配置

Actual Costing with Material Ledger 1      Purpose This configuration guide provides the information youneed to activate MaterialLedger and Actual Costing manually. The application component Actual Costing/Material Ledger fulfillstwo basic objectives

How to Change Valuation Class in Materail master

1. How to change the Valuation Class of Material Master (MM02 )  ? if you want change the valuation, then you have to change the change the valuation class, and this is not possible if you have stock. what else would you do than moving the stock from

SD从零开始38-40

[原创]SD从零开始38 创建Billing Document 根据需要BillingBilling On Request 你可以通过手工输入凭证的号码(订单号码和Delivery note,依赖于你想要执行订单相关的还是交货相关的Billing)明确地指定哪些交易将要Billing: 如果Billing无法产生,例如因为一个billing block,系统会发行一个错误日志: 到4.5版本,在为deliveries或ordersBilling时你还可以选择单个的items或者items的部分数

SAP MRP strategy group 策略组探讨

How Strategy 40 - Planning with Final Assembly Works 40: MTS ; normally , it is for standard parts . Strategy 40 :- 1. Stocks on hand reduces the PIR during MRP run.  e.g. if stock is 100 and PIR is 100, MRP run will not prompt 100 for procurement. i

MRP4 -- Dependent requirements ind. for individual and coll. reqmts

Dependent requirements ind. for individual and coll. reqmts Indicator determining whether the following requirements are allowed for the dependent requirements of the material: Individual requirements Requirement quantities of the dependent material